Construction Updates

What’s Happening on Site

We know construction can be disruptive sometimes. To help you plan ahead, here are a few quick updates about our Millersport Campus development and what you can expect.

Construction Hours

Data Center Campus Construction Hours:  

Monday – Sunday: 6 AM to 8 PM ET

Stay Informed

For construction or safety concerns, please contact us.

Key Monthly Activity

MAY '26

  • Strip and grade for trailers / laydown / mechanical yard
  • Install temporary construction fencing
  • Stone laydown / trailers / mechanical yard
  • Build access roads
  • Continue earthwork activities

    JUNE '26

    • Begin underground storm and utility work
    • North site grading and building pad prep

    JULY '26

    • Mobilize for off-site utilities and start sanitary piping

    AUGUST '26

    • Continue underground utility installation
    • Continue north buildings pad preparation

    SEPTEMBER '26

    • Mobilize for underground utility piping
    • Continue site grading activities

    OCTOBER '26

    • Continue north building pad preparation
    • Continue underground utility installation

    NOVEMBER '26

    • Continue site grading activities
    • Complete underground utilities at the site perimeter

    DECEMBER '26

    • Begin south site grading and building pad preparation
    • Begin foundation work for the north buildings

    Stay Informed

    Project Updates

    Sign up for our newsletter to receive the latest project news, key milestones and opportunities to stay engaged throughout the development process.

    Vantage is committed to your privacy. We use the informatin you provide to contact you about our relevant content, products, services and news. You may unsubscribe from these communications at any time.
    For more information, please review our privacy policy.