Construction Updates
What’s Happening on Site
We know construction can be disruptive sometimes. To help you plan ahead, here are a few quick updates about our Millersport Campus development and what you can expect.
Construction Hours
Data Center Campus Construction Hours:
Monday – Sunday: 6 AM to 8 PM ET
Stay Informed
For construction or safety concerns, please contact us.
Key Monthly Activity
MAY '26
-
Strip and grade for trailers / laydown / mechanical yard
-
Install temporary construction fencing
-
Stone laydown / trailers / mechanical yard
-
Build access roads
-
Continue earthwork activities
JUNE '26
-
Begin underground storm and utility work
-
North site grading and building pad prep
JULY '26
-
Mobilize for off-site utilities and start sanitary piping
AUGUST '26
-
Continue underground utility installation
-
Continue north buildings pad preparation
SEPTEMBER '26
-
Mobilize for underground utility piping
-
Continue site grading activities
OCTOBER '26
-
Continue north building pad preparation
-
Continue underground utility installation
NOVEMBER '26
-
Continue site grading activities
-
Complete underground utilities at the site perimeter
DECEMBER '26
-
Begin south site grading and building pad preparation
-
Begin foundation work for the north buildings